Ongoing activities on Robert Street, updated November 14, 2024
Utility work continues through spring 2025 on Robert Street between 11th and 7th Streets and through December 2024 between 7th Street and Kellogg Boulevard in advance of the reconstruction project. Please be aware of the following impacts:
Robert Street closures between 9th and 6th Streets
Closure between 9th and 7th Streets
Beginning Monday, November 18, Robert Street will close to all traffic between 9th and 7th Streets. This closure is needed for Xcel Energy and Xcel Gas to work on their utilities. Robert Street is anticipated to remain closed for up to four weeks, or until work is completed.
Closure between 7th and 6th Streets
Beginning Wednesday, November 20, Robert Street will close between 7th and 6th Streets while Xcel Gas works on their service lines. Robert Street will open to traffic on Friday, November 22.
Access on Robert Street between 9th and 6th Streets during closures
Access to driveways off Robert Street will be maintained during these closures
Intersections across Robert Street will remain open
There may be periodic, short-term delays while crews move equipment or materials through the area
Share the Robert Street Closure flyer with visitors, guests, tenants, and others.
Other traffic impacts
- Robert Street remains reduced to one lane in each direction between 11th and 9th Streets and between 6th Street and Kellogg Boulevard. Intersection restrictions/closures will occur periodically as needed for safety reasons or as required to complete construction activities.
Current activities along Robert Street:
- Between 11th and 9th Streets
- Xcel Gas is working on their utilities.
- Work between 10th and 11th Streets is complete. The pits will not be backfilled until further testing is completed on the gas lines. The road is anticipated to be restored in mid-to-late-November.
- Work between 10th and 9th Streets continues through mid-to late-November.
- At 9th Street
- The east side of the intersection is closed to/from Robert Street.
- Robert Street remains open to northbound and southbound traffic.
- Access to the west side of the intersection to/from Robert Street remains open.
- At 6th Street
- Xcel Gas is working on installing their gas main.
- Reduced to one lane across Robert Street.
- Between 6th Street and Kellogg Boulevard
- Xcel Gas is working on their utilities.
- Work between 5th and 6th Streets is complete. The pits will not be backfilled until further testing is completed on the gas lines. The road is anticipated to be restored in mid-to-late November.
- Access to local businesses is being maintained
Pedestrian Access
- Pedestrian access to properties on Robert Street is being maintained.
- Please follow signed pedestrian routes when walking or rolling near work zones.
Bus Stops