Description
Annapolis Street from Humboldt Avenue to Kansas Avenue will be reconstructed in 2024. This project will include: 

  • Reconstruction of existing pavement, curb and gutter, and sidewalks
  • Storm sewer, sanitary sewer, and watermain replacements and repairs
  • Stormwater management features to meet local and state stormwater requirements
  • Intersection improvements at the Annapolis Street, Dodd Road, and Charlton Street intersection
  • Signage, lighting and signal improvements
  • New bike lanes, requiring parking removal on north side of Annapolis
  • New trees and boulevards

Location

  • Annapolis Street from Smith Avenue to Humboldt Avenue (Phase 1)
  • Annapolis Street from Humboldt Avenue to Kansas Avenue (Phase 2)

Timeline
Community engagement began in 2021. Construction for Phase 1 from Smith Avenue to Humboldt Avenue was completed in 2023 with clean up work in 2024. Construction for Phase 2 from Humboldt Avenue to Kansas Avenue will begin in 2024.

Tags

    Joint Project with West St. Paul

    West St. Paul is taking the lead on the design and construction contract for the Annapolis Street Reconstruction project. Visit the West St. Paul project webpage for more information about the project.

    Annapolis Street Reconstruction Project