Description
Residential streets in the Cretin-Bayard area will be resurfaced in 2023 and 2024 through a process called mill and overlay to create a smoother roadway surface. Crews grind off the top layer of roadway, then replace it with a new layer of bituminous (asphalt) pavement.

As part of this project, additional pedestrian improvements will be made in some areas. Improvements will include the installation of ADA-compliant ramps to improve accessibility. Sidewalk will be added on the west side of Mount Curve Boulevard between Scheffer Avenue and Hartford Avenue. 

Location

  • 2023 - west of Cretin Avenue (Phase 1)
    • Woodlawn Avenue from Mississippi River Boulevard to Ford Parkway
    • Mount Curve Boulevard from Randolph Avenue to Ford Parkway
    • Montrose Lane from Randolph Avenue to Hartford Avenue
    • Hartford Avenue from Mississippi River Boulevard to Cretin Avenue
    • Bayard Avenue from Mount Curve Boulevard to Cretin Avenue
    • Scheffer Avenue from Mount Curve Boulevard to Cretin Avenue
    • Eleanor Avenue from Mount Curve Boulevard to Cretin Avenue
    • Pinehurst Avenue from Mount Curve Boulevard to Cretin Avenue
  • 2024 - east of Cretin Avenue (Phase 2)
    • Finn Street from Randolph Avenue to Niles Avenue and from Harford Avenue to Pinehurst Avenue
    • Juno Avenue from Cretin Avenue to Cleveland Avenue
    • Niles Avenue from Cretin Avenue to Cleveland Avenue
    • Watson Avenue from Cretin Avenue to Cleveland Avenue
    • Hartford Avenue from Cretin Avenue to Cleveland Avenue
    • Bayard Avenue from Cretin Avenue to Cleveland Avenue
    • Scheffer Avenue from Cretin Avenue to Cleveland Avenue
    • Eleanor Avenue from Cretin Avenue to Cleveland Avenue
    • Pinehurst Avenue from Cretin Avenue to Cleveland Avenue

Timeline
Summer to Fall 2023 and 2024

Tags

    New Sidewalks : No Salt

    Please refrain from using salt to remove ice on new concrete installed this year.  Salt will harm newly installed concrete and increase freeze/thaw cycles which can do further damage.

    We appreciate your assistance in helping maintain the new sidewalks.

    Construction Schedule

    • Paving is anticipated to occur on October 10, October 11, and October 14 (Thursday, Friday, and Monday)
    • No Parking signs will be posted this week on all street segments
    • Parking restrictions will be in effect Monday through Friday from 7:00 a.m. to 7:00 p.m.

    Project Updates