The City of Saint Paul will be working with a contractor to make necessary sewer repairs throughout the City. These projects are funded by the sewer utility. There are no assessments to property owners.
Streets may be closed and no parking signs posted during sewer work.
Locations
- 7th Place between Minnesota Street and Robert Street - October 16 to November 10 (weather permitting)
- Work completed:
- Wabasha Street between Congress Street and Winifred Street
- Minnesota Street at 9th Street and 11th Street
- Sumac Street and Butternut Avenue
- Woodlawn Avenue South and Ford Parkway
- West 7th Street and Montreal Avenue
- Elway Street south of West 7th Street
- St Paul Yacht Club parking lot
- Ohio Street between Alice/Winifred and Cherokee Avenue
- Pelham Boulevard and Mississippi River Boulevard
- Mississippi River Boulevard near Magoffin Avenue - 3 work sites along west side of Mississippi River Boulevard
- Mississippi River Boulevard near Itasca Avenue
- Mississippi River Boulevard near Elsie Lane
- Mississippi River Boulevard north of Cleveland Avenue South
- Minnehaha Avenue between Kennard Street and McKnight Road
- Highland Parkway between Woodlawn Avenue and Mississippi River Boulevard
- Shepard Road and Homer Street South
Timeline
December 12, 2022 to December 2023
Sewer Work on 7th Place between Minnesota Street and Robert Street
- 7th Place between Minnesota Street and Robert Street is scheduled to reopen on Friday, November 10, weather and construction permitting
- 7th Place between Minnesota Street and Robert Street is closed to all traffic
- Sidewalks will be open for pedestrians