Project Details

Description

SPRWS is committed to maintaining a reliable and efficient water system for our community. Each year we replace several miles of aging water mains that have reached the end of their service life and are prone to frequent breaks. 

The scope of this project includes: 

  • Replacement of broken steel water main at various locations along the bridge.
  • Rehabilitating approximately 800 feet of water main by inserting a liner. 

Location

Robert Street Bridge from Kellogg Blvd to Fillmore Ave 

Timeline

In progress. Expected completion by January 2025.

Contact

Project Engineer:

Rich Hibbard

richard.hibbard@ci.stpaul.mn.us

651-266-6268

Project Map

Map of Robert Street bridge water main construction project

Last Edited: November 12, 2024