The City of St Paul is replacing the Kellogg-3rd Street bridge to address the need for a more reliable connection to the City that will accommodate people walking, biking, taking transit, and driving.
Location
Kellogg-3rd Street bridge including Kellogg Boulevard from Broadway Street to Mounds Boulevard.
Timeline
- Kellogg-3rd Street bridge closed July 29, 2024.
- Kellogg-3rd Street bridge is expected to open in 2027.
- Anticipated project schedule is shown below. All dates are subject to change.
View a short video update of pouring the concrete deck for the Kellogg-3rd Street bridge - June 2026
View a short video update on the Kellogg-3rd Street bridge construction - Fall 2025
Construction Update & Detours
June 16-17 Overnight Weekday Closure of I-94 in Saint Paul for Kellogg-3rd Street Bridge Work
- 10 p.m. Tuesday, June 16 to 5 a.m. Wednesday, June 17, I-94 will be closed between I-35E and Hwy 10/61 for Kellogg-3rd Street bridge deck pour over the interstate.
- Detour for eastbound I-94 traffic: Northbound I-35E to eastbound I-694 to southbound I-694
- Detour for westbound I-94 traffic: northbound I-694 to westbound I-694 to southbound I-35E
- Local access:
- Eastbound I-94 open to the 7th Street exit and Highway 52.
- Westbound I-94 open to Mounds Boulevard exit.
- In coordination with this work, Commercial Street East from Mounds Boulevard to the Xcel Energy substation will be closed from Noon Tuesday, June 16 to 6 a.m. Wednesday, June 17. Access to Wakan Tipi and properties on Commercial Street will be from 4th Street East.
Watch the Kellogg-3rd Street Bridge deck being poured
Concrete bridge deck will be poured in nine separate events. Each pour will take over 10 hours and require over 800 cubic yards of concrete. The contractor Lunda poured the first segment of the new concrete bridge deck on April 22, 2026.
Photos of the concrete deck being poured on April 22, 2026.
Kellogg-3rd Street Bridge Closure Traffic Impacts and Detour Routes
For other downtown construction and traffic impacts, visit stpaul.gov/roadclosures.
Traffic Impacts
- Kellogg-3rd Street Bridge will be closed for approximately three years.
- Vehicles will be detoured to East 7th Street. See map for details.
- Kellogg Boulevard between Broadway and Lafayette will be closed to traffic for reconstruction starting July 29, 2024 through November 2024.
- Access to parking lots will be maintained. See detailed maps below.
- Traffic delays should be expected.
Pedestrian and Bike Impacts
Two detours are posted for pedestrians and bikes:
Parking Lot and Business Access
- Parking lots, buildings, and Union Depot will remain accessible during construction from Lowertown on the west side of the bridge. See detailed maps below to access parking lots.
- Owners and tenants immediately adjacent to the work site will receive separate notices during specific work activities that may affect their property.
Detour map for Kellogg-Third Street Bridge construction
Note Robert Street is closed for construction. Traffic is being detoured to Jackson Street southbound and Minnesota Street northbound to 7th Street.
Printable detour map for Kellogg-Third Street Bridge construction
Closures and Restrictions in Downtown Saint Paul, June 12, 2026
Construction is happening throughout downtown. Plan accordingly and expect delays. Please follow all posted signs. Road and lane closures will change as construction continues.
Additional event and construction closures that may impact access to downtown Saint Paul:
- 10 p.m. Friday, June 12 through 5 a.m. Monday, June 15, eastbound I-94 is closed between I-35E and Hwy 10/61 for bridge maintenance.
- Detour: Northbound I-35E to eastbound I-694 to southbound I-694 (See detour map)
- More information at https://www.dot.state.mn.us/metro/projects/johnirelandbridge/
- 10 p.m. Tuesday, June 16 to 5 a.m. Wednesday, June 17, I-94 closed between I-35E and Hwy 10/61 for Kellogg-3rd Street bridge deck pour over the interstate.
- Detour for eastbound I-94 traffic: Northbound I-35E to eastbound I-694 to southbound I-694
- Detour for westbound I-94 traffic: northbound I-694 to westbound I-694 to southbound I-35E
- In coordination with this work, Commercial Street East from Mounds Boulevard to the Xcel Energy substation will be closed from Noon Tuesday, June 16 to 6 a.m. Wednesday, June 17. Access to Wakan Tipi and properties on Commercial Street will be from 4th Street East.
- More information at stpaul.gov/Kellogg-3
For Saint Paul Public Works projects and links to other agencies and their projects, visit www.stpaul.gov/Construction.
For current and upcoming road closures in Saint Paul, visit www.stpaul.gov/RoadClosures.
See below for a map of the road closures and restrictions as of June 15, 2026 - same map as June 8 due to only minor changes.
No major changes to traffic impacts in downtown due to construction. There will be some short-term lane restrictions due to window washing and roofing on private buildings.
- 4th Street: Lane restrictions between St Peter and Wabasha streets for skyway painting until June 30.
- 5th Street: Lane restrictions between Wabasha and Cedar streets for Osborn Plaza.
- 6th Street:
- Lane restrictions between Jackson and Minnesota streets for Robert Street construction.
- Lane restrictions between Cedar and Wabasha streets for District Energy work.
- 7th Place: 7th Place is closed between Robert and Jackson streets as part of the Robert Street construction project.
- West 7th Street: Lane restrictions between Walnut Street and Kellogg Boulevard on West 7th for Xcel Energy work (at Chestnut Street) and sewer work (at Walnut Street).
- East 7th Street: Lane restrictions between Mounds Boulevard and Arcade Street on East 7th for MnDOT work.
- Chestnut Street: Closed at West 7th Street for Xcel Energy work.
- Jackson Street:
- Jackson Street closed to thru traffic from Kellogg Boulevard to Shepard Road for sewer pump station and floodwall work.
- Jackson Street is open to parking and properties between Kellogg Boulevard and 2nd Street. 2nd Street is open between Jackson and Sibley streets.
- For more information, visit the city’s Lowertown Floodwall webpage.
- John Ireland Bridge: Closed for MnDOT reconstruction.
- Kellogg Boulevard:
- Westbound lanes closed between West 7th Street and Wabasha Street. Eastbound open only between Wabasha Street and Washington Street. For more information about the CCB Kellogg Phase 2 project, visit stpaul.gov/ccbkellogg2.
- Lane restrictions between Broadway and Lafayette streets for Xcel Energy work.
- Kellogg Boulevard/3rd Street bridge remains closed through 2027. Kellogg Boulevard remains closed between Lafayette Street and Mounds Boulevard. For more information about the Kellogg/3rd Street Bridge project, visit: stpaul.gov/Kellogg-3.
- Lafayette Road:
- Starting June 8, road closed to all thru traffic at University Avenue.
- Road closed to northbound traffic at University Avenue.
- Robert Street: Lane restrictions between Kellogg Boulevard and 9th Street as needed for sidewalk work and final reconstruction work.
- Shepard Road:
- Westbound Shepard closed between Eagle Parkway and Sibley Street.
- Shepard Road closed to thru traffic at I-35E for MnDOT bridge reconstruction.
- Eastbound will remain open from I-35E to Highway 61.
- Eastbound Shepard traffic can access downtown from Eagle Parkway and Sibley Street, except no trucks due to tight turns and bridge height.
- Westbound Shepard traffic can access downtown from Sibley Street, except no trucks due to bridge height.
- No access from Shepard Road to I-35E southbound.
- I-35E northbound can exit to eastbound Shepard Road.
- Shepard Road detour: Lexington Parkway to West 7th Street to Otto Avenue.
- For more information, visit MnDOT's I-35E and Shepard Road webpage.
- Temperance Street: Lane restrictions between 7th and 9th streets for roofing work.
- University Avenue:
- Road closed between Lafayette Road and I-35. Access to businesses is being maintained. Printable local access map. For more information, visit www.stpaul.gov/UniversityAvenue
- Lane restrictions between I-35E and Jackson Street for utility work.
- Wabasha Street: Lane restrictions between 10th Street and Exchange Street for Xcel Energy work.
- Wacouta Street: Lane restrictions between 6th and 7th streets for Xcel Energy work. Southbound traffic only.
- Walnut Street: Sewer work at Walnut Street and West 7th Street starts June 8. Lane restrictions on West 7th Street and no thru traffic on Walnut Street.
NOTE: All construction activities and traffic impacts are weather and schedule permitting and subject to change.
Downtown Construction & Access Map for Monday, June 15, 2026 - same as the June 8, 2026 map
No major changes to traffic impacts in downtown due to construction. There will be some short-term lane restrictions due to window washing and roofing on private buildings.
Project Updates - 2026
Project Updates - 2025
Project Updates - 2024 and earlier
Final Art Designs
View the final art designs on the railings and pier columns, including the specific locations.