Eighth Street and Wall Street Reconstruction
CONSTRUCTION UPDATE AND PROJECT ARCHIVE

CONTACT INFORMATION

PROJECT DESIGN


Jesse Farrell, P.E.
Engineer
Email

900 City Hall Annex
25 West 4th Street
Saint Paul, MN 55102
Phone: 651-266-6155
Fax: 651-292-6315

PROJECT CONSTRUCTION

Tom Stadsklev, P.E.
Engineer
Email

900 City Hall Annex
25 West 4th Street
Saint Paul, MN 55102
Phone: 651-266-6078
Fax: 651-292-6315 


To view an archive of Construction Updates, click here.

This Week
  • The contractor will continue to remove pavement on Monday.
  • Saint Paul Regional Services has planned to come in on Tuesday to install a new
    water main on Wall Street.  This should take about one week to complete.
  • On Tuesday, the exit ramp from 94 eastbound to 7th Street will be minimized to one
    lane. The exit will be one lane for about three-to-four weeks until the contractor installs
    the new pavement.

Project Inspector:  Mike Van Beusekom

Cell:  651-775-6673
Office:  651-266-6083