CONSTRUCTION UPDATE AND PROJECT ARCHIVE

To view an archive of Construction Updates, click here.
       
Update 04.24.2015

The City of Saint Paul Lighting Department finished installing the light standard throughout
the project.

The street base layer was paved on Thursday.

The path was paved on Wednesday, Thursday, and Friday.

Sidewalk and pedestrian crossings were poured throughout the project.

Boulevards are being filled in with black dirt.

The signal at Broadway Street is being installed today, April 24th.

The restoration of parking lots is happening today, April 24th.

There is street sweeping throughout the project in preparation for the weekend's Art Crawl.

Planned construction for the week of April 27th - May 1st

Tree planting on the project (27 trees).

Continued restoration around parking lots and properties.

Continued restoration of boulevards, and the installation of black dirt.

Possible seeding and stabilizing of boulevard areas.

Finish concrete on project.

 The City of Saint Paul aplogizes for the inconvenience.
Please be cautious of the workers and heavy equipment in the project area.
The expected completion date is mid-May.

Project Inspector: Mike Van Beusekom        

Cell:  651-775-6673