Solar Projects and Initiatives

In 2008, the Cities of Saint Paul and Minneapolis were recognized by the U.S. Department of Energy as Solar America Cities. In partnership with other organizations, the city has become a leader in the region in installing and promoting solar energy and continues to commit to solar use. The city has completed three solar thermal projects on its facilities including the Midwest’s largest solar thermal installation on the Saint Paul RiverCentre. Many other solar projects have been completed or are in progress.

Read more about the Minneapolis Saint Paul Solar in the Cities Initiative.

City of Saint Paul Solar Projects:

          Como Lakeside.jpg  Como Park Pool.jpg        Great River Passage Solar Kiosks.jpg
Como Lakeside EV Charging Station - 2 kilowatt (kW) photovoltaic installation with 8 Solar World 250 watt modules completed April 2012.
Estimated 2,447 kWh annual production
Designed by: Westwood Professional Services
Installed by: Innovative Power Systems
Installed cost: $38,255 minus $4,275 for Xcel Energy’s Solar*Rewards rebate
Funded by: Grant from the US Department of Energy through the American Reinvestment and Recovery Act (ARRA) of 2009.
Como Park Pool - Solar hot water heating system consists of 12 panels (30 tubes per panel) evacuated solar tubes by Kingspan Product Thermomax HP200 and completed in May 2012.
Designed by: Nelson Rudie Associates
Installed by: Modern Piping
Installed cost: $150,000 grant of the $200,000 total installed cost.
Funded by: Solar Energy Legacy Grant through the Minnesota Department of Natural
Great River Passage Solar Kiosks - Four solar kiosks and interpretative signage located at the Ford Dam overlook on Mississippi River Boulevard: Crosby Farm East entrance parking lot located at Shepard Road and Elway; Shepard Road and Randolph; and Burns Avenue and Johnson Parkway were installed June 2012.
2 – 68 watt Uni-Solar photovoltaic modules completed August 2012.
Designed by: Thorbeck Architects Inc. in collaboration with Hunt Electric.
System Installer: Global Specialty Contractors Inc.
Installed cost for solar portion: $21,000
Funded by: Solar Energy Legacy Grant through the MN Department of Natural Resources.
 McMurray Field.jpg  PW Garage.jpg  Ramsey County Law Enforcement Center.png
McMurray Field EV Charging Station - 2 kilowatt (kW) photovoltaic installation with 8 Solar World 250 watt modules completed in April 2012.
Estimated 2,447 kWh annual production
Designed by: Westwood Professional Services
Installed by: Premier Electric
Installed cost: $31,635 minus $4,500 for Xcel Energy’s Solar*Rewards rebate
Funded by: Grant from the US Department of Energy through the American Reinvestment and Recovery Act (ARRA) of 2009.
Public Works Garage - 39.7 kilowatt (kW) photovoltaic installation with 169 of Schott Poly 235 modules completed August 2011.
Estimated 50,630 kWh annual production
Designed by: Westwood Professional Services
Installed by: Zenergy
Installed cost: $177,145 minus $89,640 for Xcel Energy’s Solar*Rewards rebate
Funded by: Grant from the US Department of Energy and MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.

Ramsey County Law Enforcement Center - Solar thermal installation with 35 Minnesota made Solar Skies North Star Series modules completed September 2012
Designed by: Westwood Professional Services in cooperation with District Energy St. Paul
Installed by: NAC and Bald Eagle Erectors (steel)
Installed cost: $257,900
Funded by: Grant from the US Department of Energy and the MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.
 River Centre Parking Ramp.jpg  RiverCentre Solar Thermal.jpg  Rondo Library.jpg
RiverCentre Parking Ramp - 82 kilowatt (kW) photovoltaic installation with 348 Global Watt  modules completed March 2012.
Estimated 100,000 kWh annual production
Designed by: Westwood Professional Services
Installed by: Hunt Electric and Bald Eagle Erectors (steel)
Installed cost: $629,732
Funded by: Grant from the US Department of Energy and MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.
RiverCentre Solar Thermal - 1.1 Mega Watt thermal equivalent with 144 Arcon industrial grade solar thermal panels completed in January 2011.
Designed by: District Energy St. Paul & TKDA
Installed by: Sheey Construction, Pioneer Power and Amerect Inc.
Installed cost: $2.1 Million
Funded by: $1 million Market Transformation Grant from the US Department of Energy through the American Reinvestment and Recovery Act (ARRA) of 2009 and $1.1 million match by District Energy St. Paul
Rondo Library - 39.7 kilowatt (kW) photovoltaic installation with 169 240 watt Sharp modules completed September 2011.
Estimated 50,630 kWh annual production
Designed by: Westwood Professional Services
Installed by: Zenergy
Installed cost: $184,865 minus $89,358.75 for Xcel Energy’s Solar*Rewards rebate
Funded by: Grant from the US Department of Energy and MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.
 Science Museum of MN.jpg  St Anthony Park Rec Center.jpg  Sun Ray Library.jpg
Science Museum of MN - 10.4 kilowatt (kW) photovoltaic installation with Minnesota Made 42 RAIS C tenKsolar modules completed in June 2012.
Estimated 12,770 kWh annual production
Designed by: Westwood Professional Services
Installed by: Enhanced Home Systems
Installed cost: $76,880 minus $23,467 for Xcel Energy Solar*Rewards rebate and $28,682 Minnesota Bonus
Funded by: Grant from the US Department of Energy and MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.
St. Anthony Park Recreation Center - 7.75 kilowatt (kW) photovoltaic installation with 33 Grape Solar modules completed September 2011.
Estimated 9,825 kWh annual production
Designed by: Westwood Professional Services
Installed by: Innovative Power Systems
Installed cost: $34,355 minus $17,820 for Xcel Energy’s Solar*Rewards rebate
Funded by: Grant from the US Department of Energy and MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.
Sun Ray Library EV Charging Stations - 2 kilowatt (kW) photovoltaic installation with 8 Solar World 250 watt modules completed April 2012.
Estimated 2,447 kWh annual production
Designed by: Westwood Professional Services
Installed by: Zenergy
Installed cost: $40,236
Funded by: Grant from the MN Department of Commerce
 Western District Police Station.jpg  EIC Installations.jpg
Western District Policy Station - 39.7 kilowatt (kW) photovoltaic installation with 169 Schott Poly 235 modules completed June 2011.
Estimated 50,630 kWh annual production
Designed by: Westwood Professional Services
Installed by: Zenergy
Installed cost: $177,850 minus $89,358.75 for Xcel Energy’s Solar*Rewards rebate
Funded by: Grant from the US Department of Energy and MN Department of Commerce through the American Reinvestment and Recovery Act (ARRA) of 2009.

Download solar project details here.

District Energy Solar Installation
March 18, 2011

Don’t forget to check out resources available to help with energy & energy conservation efforts.