Montana/Greenbrier RSVP
CONTACT INFORMATION

PROJECT DESIGN

Lisa Falk-Thompson, P.E.
Engineer

Email

900 City Hall Annex
25 West 4th Street
Saint Paul, MN  55102
Phone:  651-266-6117
Fax:  651-292-6315

PROJECT CONSTRUCTION

Tom Stadsklev, P.E.
Engineer

Email

900 City Hall Annex
25 West 4th Street
Saint Paul, MN  55102
Phone:  651-266-6078
Fax:  651-292-6315
CONSTRUCTION UPDATE AND PROJECT ARCHIVE

To view an archive of Construction Updates, click here.

Week of October 31st Construction Update       
       
Curb and sidewalk was placed on Ames Place and on Wheelock Parkway at Walsh
Street, Greenbrier Street, and Payne Avenue.

Boulevard grading was done on Iowa Avenue, Idaho Avenue, and California Avenue.

Driveway and alley apron patching was done.    

Week of November 7th Planned Construction

Grading and paving on Ames Place and on Wheelock Parkway at Walsh Street, 
Greenbrier Street, and Payne Avenue will be done.

The last layer of bituminous will be placed on Payne Avenue, Iowa Avenue, Idaho
Avenue, and California Avenue.

Sod will be placed on Iowa Avenue, Idaho Avenue, and California Avenue.      

Project Inspector: Steven Herbert

Cell: 651-755-5985
Office: 651-266-6072